The Collins Class Submarine Story

Home > Other > The Collins Class Submarine Story > Page 47
The Collins Class Submarine Story Page 47

by Peter Yule

by putting highly sophisticated weapons systems into Vietnam

  War era bodies has been a complete failure. By 2007 the heli-

  copters had cost over $1 billion and would not be operational

  until at least 2011, if ever.9

  Given that the submarines were the most complex and ambi-

  tious military project ever undertaken in Australia, its financial

  success can only be regarded as an extraordinary achievement.

  The project was less successful in keeping to its schedule,

  although again it compares well with other major projects. On

  average the submarines were delivered about 26 months behind

  schedule.10 However, the timetable for the withdrawal of the

  Oberons from service did not allow for any delays with the Collins

  project. One of the main reasons for the atmosphere of crisis

  around the project in the late 1990s was that the last Oberons

  were due to be withdrawn before any of the new submarines had

  been accepted by the navy as being fit for operations.

  By far the most significant problem of the Collins class was

  the failure of the combat system. If it had been delivered on time

  and with the capabilities asked for by the navy and promised by

  the contractors, then the teething problems with the submarines

  would have been regarded as being normal for a ‘first of class’. But

  while the combat system caused great difficulties, the ship control

  and management system, which was initially regarded as a greater

  risk, has been a notable success.

  An often forgotten reality is that, of the myriad systems that

  make up the submarines, the vast majority have worked smoothly

  from the first; a small proportion of systems had problems that

  326

  T H E C O L L I N S C L A S S S U B M A R I N E S T O R Y

  were quickly resolved, and an even smaller proportion – diesel

  engines, propellers and hydrodynamics – had more serious prob-

  lems. These problems lay at the heart of the dissension of the late

  1990s and were eventually resolved with vital contributions from

  the technical staff on the project team, Australian defence scien-

  tists and the US Navy. It is often forgotten, in the rush to apportion

  blame for the things that went wrong, that the vast majority of

  things went right and that Kockums as the designers and ASC as

  the contractors – with the guidance of the project team – were

  responsible for these. If the project was a success, the greatest

  credit should go to the designers and the builders.

  Much of the dissonance within the submarine project stemmed

  from the differing aims and ambitions of groups and organisations

  involved. At the two extremes: the submariners assumed that the

  only purpose of the project was to give them fabulous new sub-

  marines, but to the left of the Labor Party and the trade unions,

  which gave the project critical support in the early days, the central

  purposes of the project were to give jobs to metal workers, revive

  manufacturing industry and forge closer links with Sweden, the

  socialist paradise. The navy was divided between the submariners

  and the surface sailors, many of whom saw the submarines as tak-

  ing money that could be used for surface ships, while within the

  Defence Department many bureaucrats opposed the fundamental

  premises of the project, notably the requirement for large, long-

  range submarines and the arguments for building in Australia.

  These differences were compounded when the project became a

  political punching bag after its godfather, Kim Beazley, became

  opposition leader in 1996.

  In spite of the difficulties, problems and obstacles, there is an

  overwhelming consensus among military insiders (in stark con-

  trast to the view of the general public) that the submarine project

  was a great success. It is now regularly claimed that the Collins

  class are ‘the finest conventional submarines in the world’.11 This

  claim is difficult to assess, if only because they are like no other

  conventional submarines as the navy demanded, and received,

  unique submarines for a unique strategic situation. There are now

  newer submarines with some features that are clearly superior

  to the Collins class, but Collins will have the range, submerged

  endurance, battery recharging rate and speed to suit the needs of

  the Australian (and American) navies for many years to come.

  C O M P A R I S O N A N D R E T R O S P E C T

  327

  The other claim made by enthusiasts for the Collins class is

  that the submarine project ranks alongside the Snowy Moun-

  tains Scheme as a nation-building engineering achievement. This

  proposition is partially negated by the inherently unproductive

  and wasteful nature of military spending (however necessary it

  may be), which diverts resources from more productive uses.

  The Snowy Mountains Scheme was totally paid for with the rev-

  enue from hydro-electricity, allowing an average of over 2 mil-

  lion megalitres of water annually to be supplied to the states at

  no charge. In stark contrast, the submarines were a charge on

  taxpayers and they continue to demand huge amounts of money.

  Large and continuing spending is needed to maintain the effective-

  ness of all complex military equipment, and there are few systems

  more complex – or having higher demands for safe operation –

  than a submarine. During 2007–08 the submarine fleet will cost

  $322 million to maintain, 38 per cent more than the eight Anzac

  frigates and the single most expensive class of equipment in the

  defence force.12

  Nonetheless there are parallels between the projects. The

  Snowy Mountains Scheme was the headline project of Australia’s

  rapid economic development in the years after the Second World

  War, while the submarine project was a centrepiece of economic

  restructuring following the malaise of the 1970s and early 1980s.

  At a time when Australian manufacturing industry appeared to

  be in terminal decline with outdated technology and equipment,

  poor industrial relations and dependence on tariffs and subsidies,

  the Collins project was deliberately structured to demonstrate an

  alternative approach. When choosing the consortium to design

  and build the submarine, issues of modern construction tech-

  niques, technology transfer and Australian industry involvement

  were as important as the design itself. A central and startling aim

  of the project was that 70 per cent of the money should be spent in

  Australia. Previous projects had uniformly failed to meet far less

  ambitious targets, but the Collins project achieved its Australian

  content ambitions with a margin to spare. This money was paid to

  many sub-contractors large and small throughout Australia, and

  with the money came new technology and training, and an empha-

  sis on quality control previously foreign to Australian industry.

  The Collins project was the first time that Australia developed

  a unique design for the country’s specific military requirements

  328

  T H E C O L L I N S C L A S S S U B M A R I N E S T O
R Y

  rather than buying a product designed for another country’s needs.

  This presented great challenges to the navy, which took many

  years to understand and accept the demands of being the parent

  navy for the Collins class, but it had the consequence that Aus-

  tralian industry was forced to expand its horizons in many direc-

  tions. ASC and its sub-contractors developed new skills in project

  management, design, manufacturing and systems integration, and

  ASC built up the management abilities and systems to construct

  six submarines in Australia and manage the hundreds of overseas

  and Australian suppliers. This involved the development of a myr-

  iad of relationships between overseas and Australian companies

  embracing 10 countries with diverse cultures, standards and prac-

  tices. Australian companies and Australian workers successfully

  completed a wide array of challenging processes, perhaps most

  notably the manufacture and fabrication of steel for the pressure

  hulls. The welding on all the Australian-built sections of the sub-

  marines is probably better than has been achieved anywhere else

  in the world.

  In many areas of the project Australian research and develop-

  ment was crucial, notably in the work of DSTO and the techni-

  cal staff of the project office. In many different ways the work

  of DSTO scientists focused on dealing with the unique nature

  of the project. In earlier days it provided the technological basis

  to do things never before attempted in Australia. In later times,

  DSTO grappled with and overcame the unexpected problems that

  inevitably arose when doing things for the first time. This effort

  demonstrated the importance of sustaining in Australia a body of

  technical knowledge, a mode of operation and links with indus-

  try and overseas colleagues and institutions to provide a range of

  options and answers.

  The submarine project did not achieve all the high hopes held

  out for it in the mid-1980s, but given the scale of the ambitions this

  is not surprising. Perhaps if the ambitions had not been pitched at

  such a high level the true scale of the achievement might be recog-

  nised, because there are many things in the Collins story that are

  remarkable. For the first time the Australian navy has sustained

  a submarine force from one class of boat to another. Even if not

  entirely accepted throughout the navy, the role and effectiveness

  of submarines in Australia’s defence has been established. That

  this should be done through a full-scale industrial program to

  C O M P A R I S O N A N D R E T R O S P E C T

  329

  produce what Australia had never before produced is even more

  remarkable. Australia now has a type of submarine with a range,

  endurance and speed that cannot be matched by any other con-

  ventional submarine. That the accomplishment was marked by

  acrimony, controversy and bitterness perhaps simply reflects the

  magnitude of the project and the scale of the achievement. That

  there is a pervasive public perception of failure is an irony that

  the many people who dedicated years of their lives to the project

  find hard to comprehend.

  Perhaps the greatest irony of the project is that the crisis of

  the late 1990s paved the way for not only building another class

  of submarines in Australia, but designing them here as well. The

  problems of the submarines, and the impasse reached between

  Kockums and the Commonwealth over the solutions to the prob-

  lems, forced Australia to look to its own resources. This resulted

  in a great expansion of research and development capacity on

  submarine issues and ASC’s recognition as the design authority

  for the Collins class. Both major political parties now feel owner-

  ship of the submarines – Labor for building them and the Liber-

  als for fixing them – and there is a consensus that the next class

  of submarines should be designed and built in Australia. In the

  heat and noise of the late 1990s this would have been almost

  unimaginable.

  N O T E S

  Introduction

  1. It remained so until the goverment’s decision in 2007 to spend $6.6 billion on F/A18 F Super Hornets and $8 billion on air warfare destroyers.

  Chapter 1. ‘The one class of vessel that it is impossible

  to build in Australia: Australia’s early submarines

  1. Melbourne Age, 12 July 1928, Sydney Sun, 12 October 1928.

  2. Michael W. D. White, Australian submarines: A history, Australian Government Publishing Service, Canberra, 1992, p. 157.

  3. Letter of 20 April 1904, in Lord Fisher, Records, Hodder & Stoughton, London, 1919, p. 175.

  4. Creswell to Minister for Defence, 13 December 1907, National Archives of

  Australia (NAA) Series MP178, item 2215/3/95; also NAA series MP178/2,

  item 2286/3/54.

  5. Jan Rueger, ‘The last word in outward splendour: the cult of the Navy and the imperial age’, in David Stevens & John Reeve (eds), The navy and the nation: The influence of the navy on modern Australia, Allen & Unwin, Sydney, 2005, p. 51.

  6. ibid.

  7. John Jeremy, Cockatoo Island: Sydney’s historic dockyard, 2nd edn, UNSW

  Press, Sydney, 2005, pp. 30–1.

  8. Letter from A. Dawson, a director of Vickers, to Captain Robert Collins

  (Australian naval representative in London), 24 September 1907, NAA series

  MP178, item 2286/3/54.

  9. The full story of AE2 and its crew is told in Fred & Elizabeth Brenchley, Stoker’s submarine, HarperCollins, Sydney, 2001. Commander Stoker gave a dramatic first person account in H. G. Stoker, Straws in the wind, Herbert Jenkins, London, 1925. For an assessment of the strategic significance of AE2’s achievement see

  T. R. Frame & G. J. Swinden, First in, last out: The navy at Gallipoli, Kangaroo Press, Sydney, 1990, pp. 101–3.

  10. NAA series MP1049/1, item 1920/0416, ‘Submarines AE1 and AE2 –

  replacement of.’

  11. Chris Clark, ‘Vice Admiral Sir William Clarkson, KBE, CMG, RAN: building

  ships for the navy and the nation,’ in Stevens & Reeve, n 5 above, pp. 314–16; C. Forster, ‘Australian manufacturing and the war of 1914–18’, Economic

  record, XXIX, 1953, pp. 211–30.

  12. J. D. Perkins, ‘The Canadian-built British H boats’,

  http://www.gwpda.org/naval/cdnhboat.htm.

  330

  N O T E S T O P A G E S 7 – 1 6

  331

  13. Commonwealth parliamentary debates, House of Representatives,

  27 May 1915, p. 3498.

  14. ibid., and Jeremy, Cockatoo Island, n 7 above, p. 144.

  15. White, Australian submarines, n 2 above, chs. 10 and 11.

  16. Chief of Naval Staff to Third Naval Member, 23 November 1920, NAA series

  MP1049/1, item 1920/0416, ‘Construction of warships in Australia, 1914–19’.

  17. Third Naval Member to Chief of Naval Staff, 25 November 1920, ibid.

  18. General manager, Cockatoo Island Dockyard to Secretary, Department of the Navy, 16 December 1920, in ibid.

  19. Quoted in White, Australian submarines, n 2 above, pp. 123–4. The source is given as a report in NAA series MP981, item 603/223/305. Unfortunately, this

  file has been missing since 1994, so it has not been possible to read the full report.

  20. Oxley was torpedoed in the North
Sea by another British submarine on 14

  September 1939; Otway survived the war and ‘ended her days as a hulk abandoned on a mud bank somewhere near Dar es Salaam, Africa’. White,

  Australian submarines, n 2 above, p. 164.

  21. John Jeremy, ‘Australian shipbuilding and the impact of the Second World War’, in Stevens & Reeve, The navy and the nation, n 5 above, pp. 185–209.

  22. David Stevens, The Royal Australian Navy, The Australian Centenary History of Defence, vol. III, Oxford University Press, Melbourne, 2001, pp. 168–70.

  23. Jeremy, ‘Australian shipbuilding and the impact of the Second World War’, in Stevens & Reeve, The navy and the nation, n 5 above,

  pp. 197–8.

  Chapter 2. Australia’s Oberon class submarines

  1. John Jeremy, Cockatoo Island: Sydney’s historic dockyard, 2nd edn, UNSW

  Press, Sydney, 2005 , pp. 146–7.

  2. Attachment to Chiefs of Staff Committee Minute 19 October 1959, NAA series A8447, item 113/1959, ‘Composition of the Forces – proposed introduction of a submarine force into the RAN’.

  3. Commonwealth parliamentary debates, House of Representatives,

  27 March 1962, p. 946.

  4. Information from Henry Cook and Bill Owen. These former Royal Navy

  submarine commanders became the first and second directors of submarine

  policy in the RAN.

  5. Weymouth to Opperman, 23 January 1963, NAA series A1945, item 243/3,

  ‘Construction of submarines for RAN’.

  6. The secretary of the Department of Defence explained to his minister on 31

  October 1963, ‘It is considered important to be able to demonstrate that every effort has been made to ascertain whether at least some portion of submarine

  construction could be undertaken in Australia . . . the Navy considers this action will merely waste time’, in ibid.

  7. Melbourne Sun, 24 January 1963.

  8. Melbourne Age, 12 February 1963.

  9. ibid., 16 February 1963.

  10. Canberra Times, 11 February 1963.

  11. Melbourne Age, 13 February 1963.

  12. Department of the Navy, 4 February 1963, NAA series A1945, item 243/3,

  ‘Construction of submarines for RAN’.

  13. Report for the Joint War Production Committee by the Department of the Navy, October 1963, in ibid.

  332

  N O T E S T O P A G E S 1 6 – 2 7

  14. Secretary, Department of the Navy to Secretary, Department of Defence, 14 June 1963, in ibid.

  15. Joint War Production Committee Minute, 29 October 1963, in ibid.

 

‹ Prev