The Goal
Page 24
"We can only use as much as the market demand can ab- sorb," I say.
"Correct. By definition, Y has excess capacity," says Jonah. "So if you work Y to the maximum, you once again get excess
214
inventory. And this time you end up, not with excess work-in- process, but with excess finished goods. The constraint here is not in production. The constraint is marketing's ability to sell."
As he says this, I'm thinking to myself about the finished goods we've got crammed into warehouses. At least two-thirds of those inventories are products made entirely with non-bottleneck parts. By running non-bottlenecks for "efficiency," we've built inventories far in excess of demand. And what about the remain- ing third of our finished goods? They have bottleneck parts, but most of those products have been sitting on the shelf now for a couple of years. They're obsolete. Out of 1,500 or so units in stock, we're lucky if we can sell ten a month. Just about all of the competitive products with bottleneck parts are sold virtually as soon as they come out of final assembly. A few of them sit in the warehouse a day or two before they go to the customer, but due to the backlog, not many.
I look at Jonah. To the four diagrams on the floor, he has now added numbers so that together they look like this...
Jonah says, "We've examined four linear combinations in- volving X and Y. Now, of course, we can create endless combina- tions of X and Y. But the four in front of us are fundamental enough that we don't have to go any further. Because if we use these like building blocks, we can represent any manufacturing situation. We don't have to look at trillions of combinations of X and Y to find what is universally true in all of them; we can generalize the truth simply by identifying what happens in each of these four cases. Can you tell me what you have noticed to be similar in all of them?"
Stacey points out immediately that in no case does Y ever determine throughput for the system. Whenever it's possible to
215
activate Y above the level of X, doing so results only in excess inventory, not in greater throughput.
"Yes, and if we follow that thought to a logical conclusion," says Jonah, "we can form a simple rule which will be true in every case: the level of utilization of a non-bottleneck is not determined by its own potential, but by some other constraint in the system."
He points to the NCX-10.
"A major constraint here in your system is this machine," says Jonah. "When you make a non-bottleneck do more work than this machine, you are not increasing productivity. On the contrary, you are doing exactly the opposite. You are creating excess inventory, which is against the goal."
"But what are we supposed to do?" asks Bob. "If we don't keep our people working, we'll have idle time, and idle time will lower our efficiencies."
"So what?" asks Jonah.
Donovan is taken aback. "Beg pardon, but how the hell can you say that?"
"Just take a look behind you," says Jonah. "Take a look at the monster you've made. It did not create itself. You have created this mountain of inventory with your own decisions. And why? Because of the wrong assumption that you must make the work- ers produce one hundred percent of the time, or else get rid of them to 'save' money."
Lou says, "Well, granted that maybe one hundred percent is unrealistic. We just ask for some acceptable percentage, say, ninety percent."
"Why is ninety percent acceptable?" asks Jonah. "Why not sixty percent, or twenty-five? The numbers are meaningless un- less they are based upon the constraints of the system. With enough raw materials, you can keep one worker busy from now until retirement. But should you do it? Not if you want to make money."
Then Ralph suggests, "What you're saying is that making an employee work and profiting from that work are two different things."
"Yes, and that's a very close approximation of the second rule we can logically derive from the four combinations of X and Y we talked about," says Jonah. "Putting it precisely, activating a resource and utilizing a resource are not synonymous."
He explains that in both rules, "utilizing" a resource means
216
making use of the resource in a way that moves the system toward the goal. "Activating" a resource is like pressing the ON switch of a machine; it runs whether or not there is any benefit to be de- rived from the work it's doing. So, really, activating a non-bottle- neck to its maximum is an act of maximum stupidity.
"And the implication of these rules is that we must n o t seek to optimize every resource in the system," says Jonah. "A system of local optimums is not an optimum system at all; it is a very ineffi- cient system."
"Okay," I say, "but how does knowing this help us get the missing parts unstuck at the milling machines and moved to final assembly?"
Jonah says, "Think about the build-up of inventory both here and at your milling machines in terms of these two rules we just talked about."
"I think I see the cause of the problem," Stacey says, "We're releasing material faster than the bottlenecks can process it."
"Yes," says Jonah. "You are sending work onto the floor whenever n o n -bottlenecks are running out of work to do."
I say, "Granted, but the milling machines are a bottleneck."
Jonah shakes his head and says, "No, they are not-as evi- denced by all this excess inventory behind you. You see, the mill- ing machines are not intrinsically a bottleneck. You have turned them into one."
He tells us that with an increase in throughput, it is possible to create new bottlenecks. But most plants have so much extra capacity that it takes an enormous increase in throughput before this happens. We've only had a twenty percent increase. When I had talked to him by phone, he thought it unlikely a new bottle- neck would have occurred.
What happened was that even as throughput increased, we continued loading the plant with inventory as if we expected to keep all our workers fully activated. This increased the load dumped upon the milling machines and pushed them beyond their capacity. The first-priority, red-tagged parts were pro- cessed, but the green-tagged parts piled up. So not only did we get excess inventory at the NCX-10 and at heat-treat, but due to the volume of bottleneck parts, we clogged the flow at another work center and prevented non-bottleneck parts from reaching assembly.
When he's finished, I say, "All right, I see now the error of
217
our ways . Can you tell us what we should do to correct the prob- lem?"
"I want you all to think about it as we walk back to your conference room and then we'll talk about what you should do," says Jonah. "The solution is fairly simple."
218
26
Just how simple the solution is doesn't become apparent to me until I'm home that night. I'm sitting at the kitchen table with a pad of paper and a pencil thinking about what was suggested today when Sharon comes in.
"Hi," she says as she sits down.
"Hi," I say back. "What's up?"
"Not much," she says. "Just wondered what you were do- ing."
"I'm working," I tell her.
"Can I help?" she asks.
"Well... I don't know," I say. "It's kind of technical. I think you'll probably be bored by it."
"Oh," she says. "Does that mean you want me to leave?"
Guilt strikes.
"No, not if you want to stay," I tell her. "Do you want to try to solve a problem?"
"Okay," she says, brightening.
I say, "All right. Let me think of how to put this to you. Do you know about the scout hike Dave and I were on?"
"She doesn't, but I do!" says Dave, racing into the kitchen. He skids to a stop on the smooth floor and says, "Sharon doesn't know anything about the hike. But I can help you."
I say, "Son, I think there is a career for you in sales."
Sharon indignantly says, "Yes, I d o know about the hike."
"You weren't even there," says Dave.
"I've heard everybody talk about it," she says.
"Okay, b o th of you can work on this," I s
ay. "Here's the prob- lem: We've got a line of kids on a hike in the woods. In the middle of the line, we've got Herbie. We've already taken the pack off Herbie's back to help him go faster, but he's still the slowest. Everybody wants to go faster than Herbie. But if that happens, the line will spread out and some of the kids will get lost. For one reason or another, we can't move Herbie from the middle of the line. Now, how do we keep the line from spread- ing?"
They both become thoughtful.
219
I say, "All right, now both of you go into the other room. I'll give you ten minutes, and then we'll see which one of you comes up with the best idea to keep everyone together in the line."
"What does the winner get?" asks Dave.
"Well... anything within reason."
"Anything?" asks Sharon.
"Within reason," I repeat.
So they leave and I get about ten minutes of peace and quiet. Then I see the two faces looking around the corner.
"Ready?" I ask.
They come in and sit down at the kitchen table with me.
"Want to hear my idea?" asks Sharon.
"My idea is better," says Dave.
"It is not!" she tells him.
"Okay, enough!" I say. "What's your idea, Sharon?"
Sharon says, "A drummer."
"Pardon me?"
"You know... like in a parade," she says.
"Oh, I know what you mean," I say, realizing what she has in mind. "There aren't any gaps in a parade. Everybody is marching in step."
Sharon beams. Dave gives her a dirty look.
"So everybody's marching in step... to a beat," I say, thinking out loud. "Sure. But how do you keep the people in front of Herbie from setting a faster pace?"
"You have Herbie beat the drum," says Sharon.
I think about it and say, "Yeah, that's not bad."
"But my idea is better," says Dave.
I turn to him. "Okay, wise guy, what's your idea?"
"Tie ropes to everyone," says Dave.
"Ropes?"
"You know, like mountain climbers," he says. "You tie every- one together at the waist with one long rope. So, that way, no one could get left behind, and nobody could speed up without every- body speeding up."
I say, "Hmmm... that's very good."
It would mean that the line-which would translate to the total inventory in the plant-could never be longer than the rope. And the rope, of course, could be of a pre-determined length, which means we could control it with precision. Everyone
220
would have to walk at the same speed . I look at Dave, a little in awe of his creativity.
"Come to think of it, the rope makes it sound like having physical links between all the equipment," I tell him, "which is like an assembly line."
"Yeah, an assembly line," says Dave. "Didn't you tell me once that an assembly line is supposed to be the best way to make things?"
"Well, yes, it's the most efficient way to manufacture," I say. "In fact, we use that approach when we do the final assembly for most of our products. The problem is that an assembly line won't work throughout the whole plant."
"Oh," says Dave.
"But those are both good ideas you two thought up," I tell them. "In fact, if we changed each of your ideas just a little bit we'd almost have the solution suggested to us today."
"Like how?" asks Sharon.
"See, to keep the line from spreading, it actually wouldn't be necessary to keep everyone marching to exactly the same step or to keep everyone tied to the rope," I tell them. "What we really have to do is just keep the kid at the front of the line from walk- ing faster than Herbie. If we can do that, then everybody will stay together."
"So we just tie the rope from Herbie to the kid at the front," says Dave.
"Or, maybe Herbie and the boy at the front of the line have signals," says Sharon. "When the boy in front goes too fast, Herbie tells him to wait or slow down."
"That's right," I say. "Both of you figured it out."
"So what do we both win?" asks Sharon.
"What do you want?" I ask. "A pizza with everything? A night at the movies?"
They're quiet for a moment.
"The movies sound good," says Sharon, "but what I'd really like is if you could get Mom to come home again."
Now it gets very quiet.
Dave says finally, "But if you can't, we'll understand."
"Well, I'm doing my best," I say. "Meanwhile, how about the movies?"
After the kids have gone to bed, I sit up wondering for the hundredth time whether Julie will come back. Compared with
221
my marital difficulties, the inventory problem at the plant seems simple-or at least it seems simple now. I guess every problem is easy once you've figured it out.
We are, in effect, going to do what my two kids came up with. The Herbies (the bottlenecks) are going to tell us when to let more inventory into the system-except we're going to use the aid of computers instead of drums and ropes.
After we returned to the conference room in the office build- ing today, we started talking, and we all agreed that we're obvi- ously releasing too much material. We don't need five or six weeks of inventory in front of the bottleneck to keep it produc- tive.
"If we can withhold materials for red parts, instead of push- ing them out there as soon as the first non-bottleneck has nothing to do," said Stacey, "the milling machines will then have time to work on the green parts. And the parts we're missing will reach assembly with no problem."
Jonah nodded and said, "That's right. What you have to do is find a way to release the material for the red parts according to the rate at which the bottlenecks need material-and strictly at that rate."
Then I said, "Fine, but how do we time each release of mate- rial so it arrives at the bottleneck when it's needed?"
Stacey said, "I'm not sure, but I see what you're worried about. We don't want the opposite problem of no work in front of the bottleneck."
"Hell, we got at least a month before that happens, even if we released no more red tags from today on," said Bob. "But I know what you mean. If we idle the bottleneck, we lose throughput."
"What we need," I said, "is some kind of signal to link the bottlenecks with the release-of-materials schedule."
Then Ralph, to my surprise, spoke up and said, "Excuse me, this is just a thought. But maybe we can predict when to release material by some kind of system based on the data we've kept on both the bottlenecks."
I asked him what he was getting at.
He said, "Well, since we started keeping data on the bottle- necks, I've been noticing I'm able to predict several weeks in advance what each bottleneck will be working on at a particular time. See, as long as I know exactly what's in queue, I just take
222
the average setup and process times for each type of part, and I'm able to calculate when each batch should clear the bottleneck. Because we're only dealing with one work center, with much less dependency, we can average the statistical fluctuations and get a better degree of accuracy."
Ralph went on to say that he knows from observation it takes about two weeks, plus or minus a day or two, for material to reach the bottlenecks from the first operations.
"So by adding two weeks to the setup and process times of what's in queue at the bottleneck," said Ralph, "I know how long it will take until the bottleneck is actually working on material we release. And as each batch leaves the bottleneck, we can update our information and calculate a date when Stacey should release more red-tag material."
Jonah looked at Ralph and said, "that's excellent!"
"Ralph," I said, "that's terrific. How accurate do you really think we can be with this?"
"I'd say we'd be accurate to within plus or minus a day," he said. "So if we keep, say, a three-day stock of work-in-process in front of each bottleneck, we should be safe."
Everyone was telling Ralph how impressed they were when Jonah said, "But, in fact
, Ralph, you can do much more than that with the same information."
"Like what?" asked Ralph.
Jonah said, "You can also attack the inventory problems in front of assembly."
"You mean we not only can do something about excess in- ventory on the bottleneck parts, but on the non-bottleneck parts as well?" I asked.
"Exactly," said Jonah.
But Ralph said, "Sorry, folks, I'm not sure how I'd do that."
Then Jonah explained it to him-and all of us. If Ralph can determine a schedule for releasing red-tag materials based on the bottlenecks, he can also determine a schedule for final assembly. Once he knows when the bottleneck parts will reach final assem- bly, he can calculate backwards and determine the release of the non-bottleneck materials along each of their routes. In this way, the bottlenecks will be determining the release of all the materials in the plant.
I said, "You know, that's going to produce the same effect as
223
moving the bottlenecks to the head of production, which is what I'd intended for us to do."
"Yeah, it sounds good," said Ralph. "But I have to warn you, I can't say how long it'll take before I can do all that. I mean, I can have schedule for the red-tagged materials worked out in a fairly short order. The rest of it will take awhile."
"Aw, come on, Ralphie," said Bob, "a computer wiz like you ought to be able to crank that out in no time."
"I can crank something out in no time," said Ralph, "but I'm not going to promise it'll work."
I told him, "Relax; as long as we ease the load on the milling machines, we'll be okay for the short haul. That'll give you the time to get something basic in place."